Code of Maryland Regulations (Last Updated: April 6, 2021) |
Title 20. Public Service Commission |
Subtitle 50. SERVICE SUPPLIED BY ELECTRIC COMPANIES |
Chapter 20.50.09. Small Generator Interconnection Standards |
Sec. 20.50.09.00. Notations |
Sec. 20.50.09.01. Scope |
Sec. 20.50.09.02. Definitions |
Sec. 20.50.09.03. Acceptable Standards |
Sec. 20.50.09.04. Interconnection Requests |
Sec. 20.50.09.05. Interconnection Request Processing Fees |
Sec. 20.50.09.06. General Requirements |
Sec. 20.50.09.07. Lab-Certified and Field-Approved Equipment |
Sec. 20.50.09.08. Determination of Interconnection Jurisdiction and Level of Utility Review of Interconnection Request |
Sec. 20.50.09.09. Level 1 Review |
Sec. 20.50.09.10. Level 2 Review |
Sec. 20.50.09.11. Level 3 Review |
Sec. 20.50.09.12. Level 4 Study Review |
Sec. 20.50.09.13. Dispute Resolution |
Sec. 20.50.09.14. Record Retention and Reporting Requirements |
Sec. 20.50.09.9999. Administrative History |