  • A. An application for a proposed transmission line or modification to an existing transmission line shall include:

    (1) An explanation of the need for the project in meeting demands for service;

    (2) A description of the effect of the project on system stability and reliability;

    (3) A description of the consequences if the project is delayed or not approved;

    (4) An explanation of the cost effectiveness of the project, including an estimate of capital cost and annual operating cost; and

    (5) A description of the impact of the project on the economies of the State.