Sec. 20.79.01.06. Deadlines
Latest version.
-
A. Unless otherwise directed by the Commission, a decision on an application for a Certificate of Public Convenience and Necessity for the construction of an electric generating station shall be rendered not later than 365 days from the date a complete application is filed.
B. Unless otherwise directed by the Commission, a decision on an application for modification of an electric generating station shall be rendered not later than 150 days from the date a complete application is filed.