Sec. 14.39.04.09. Fast Track  


Latest version.
  • A. General. Fast track means a modification to a project delivery method in which portions of a project begin construction while other portions of the project are still in the design phase.

    B. Notice to IAC.

    (1) The LEA shall submit written notice to the IAC or its designee of its intent to use fast track not later than 3 months before the start of construction.

    (2) The LEA may request a shorter notice period which the IAC or its designee may approve in its sole discretion.

    (3) The written notice shall include at a minimum the proposed:

    (a) Brief description of the overall project phasing;

    (b) Schedule for the submission of plans and specifications for review by IAC or its designee; and

    (c) Solicitation schedule.

    (4) The LEA shall acknowledge in the notice that the State is not responsible for any project cost overruns.

    (5) The LEA shall notify the IAC or its designee of any schedule changes.

    (6) The LEA shall ensure that local permit agencies will accept the phasing schedule proposed by the LEA.